Construction Process 2017-2020
Watch Construction Videos of Hijos de Dios Community Centre
HERE
October 2020
September 2020
August 2020
July 2020
June 2020
May 2020
April 2020
March 2020
February 2020
January 2020
December 2019
November 2019
October 2019
September 2019
August 2019
July 2019
June 2019
May 2019
April 2019
March 2019
February 2019
January 2019
December 2018
November 2018
October 2018
August September 2018
July 2018
Sidewalk coverage, bridge, stairs and second level wall completed and the foundation of the dining area and kitchen started.
June 2018
Sidewalk posts, bridge, stairs to second levels and storage for recycled wood and Obstacle Course.
May 2018
Finish painting all the houses, front entrance finished and Day of the Worker
April 2018
Shower shelves made, planters constructed, gravel around houses and front entrance pad constructed
March 2018
Sidewalk finished and Houses Painted
February 2018
Sidewalk Started
January 2018
Storage Building Completed and Trees Removed
Photos of the Construction Process 2017
December 2017
Building the new Storage/Supply Organizing Building
November 2017
Building the new Storage/Supply Organizing Building
October 2017
Replacing Storage Building
_____________________________________________________________________________________________________
February - March 2017
Heightening of Wall
Removing and Pouring Concrete at Front Entrance
April 2017
Replacing Roof of first house and bringing up playground from old site.
Replacing the Roof (Making it level)
Putting on Roof
May 2017
Putting on Roof: Final Part
Pouring Roof #1 and 2nd roof off
House #2: Wall Leveling
Walls Leveled, Mudded and rebar tied
June 2017
House #1 Repello and House #2 roof delivered
House #2 roof put on (Lots of men working as rain is coming)
House #1 roof Completed. House #2 Roof 75% Completed. House #3 Started
House #3 Roof Leveled off and Rain on the street
House #3 Roof Ready to go.
July 2017
House #3 Roof Done.
Stages of each home. House #1: Completed. House #2: 90% Competed. House #3: 75% Completed. House #4: Ready to start.
House #4: Roof removed and Leveled.
August 2017
House #4: Roof Poured.
Be the first to comment